Module 3 · Production Systems and Diagnosis

Takt time and bottlenecks

Use customer demand to find the required pace, then test whether the production line can keep up.

Three terms to know

Takt time
The time available per unit to meet customer demand.
Cycle time
The time a station takes to complete one unit.
Bottleneck
The station that limits the line’s output. With one resource at each step under steady conditions, the longest cycle time sets the line’s capacity.

Worked example

A team has 3,600 production seconds to make 60 units.

3,600 ÷ 60 = 60 s/unit

The stations are Cutting (45 s), Assembly (60 s), and Inspection (50 s). Assembly is the bottleneck. Line capacity is 60 units per hour. The line meets demand exactly.

This example assumes steady production with one resource at each station and no downtime or defects.

Open the lab

Course reference · Types of production systems, Module 3, slides 58–72.

Module 3 review

The Toyota Production System and the 4P model

The Toyota Production System (TPS) uses just-in-time and jidoka to deliver quality, lower cost, and shorter lead time. Standardized work, leveling, and operational stability support those two pillars. People improve the system through daily kaizen. The Toyota Way’s 4P model describes the management practices that sustain this work across the organization.

Just-in-time and jidoka
Just-in-time supplies what is needed when and in the quantity needed. Jidoka builds quality into the process by detecting an abnormality, stopping, containing the problem, and addressing its cause.
Philosophy (principle 1)
Make decisions that protect the organization’s long-term ability to create value.
Process (principles 2–8)
Create continuous flow, use pull, level the workload (heijunka), stop to fix problems, standardize work, make abnormalities visible, and use tested technology that supports people and processes.
People and partners (principles 9–11)
Develop leaders who understand and teach the work, build capable teams, and help suppliers and partners improve.
Problem solving (principles 12–14)
Go to the source and observe (genchi genbutsu), build agreement before acting, then implement promptly and learn through reflection (hansei) and continuous improvement (kaizen).

Production strategies and facility layouts

A manufacturing strategy determines which work starts after a customer order. Engineer-to-order starts with a custom design, make-to-order starts fabrication, assemble-to-order starts final assembly using stock components, and make-to-stock ships from finished inventory. Layout is a separate decision informed by volume, variety, and the route work takes.

Product layout
Arrange dedicated stations in the sequence the product needs. This fits high-volume, repeatable work.
Process layout
Group similar equipment by function. Different jobs can take different routes through the facility.
Cellular layout
Group the people and equipment needed for a family of products with similar processing requirements.
Fixed-position layout
Keep a large or complex product in one place and bring people, equipment, and materials to it.
Worked example

A manufacturer stocks common modules and installs customer-selected options after an order. Which strategy fits?

Assemble-to-order. The modules are available as inventory, so the customer’s lead time covers final configuration and assembly.

Push, pull, and kanban

Push releases work against a plan based on forecast or scheduled demand. Material requirements planning (MRP) works backward from due dates, using the bill of materials and lead times to determine what to release and when. Pull authorizes work when downstream demand or consumption calls for it. Material flows downstream and the replenishment signal travels upstream.

Kanban
A card, container signal, or electronic instruction that authorizes a specified movement or replenishment quantity. Limiting the signals in circulation limits authorized work in process.
Supermarket
A controlled buffer from which downstream work withdraws parts. Withdrawal triggers replenishment upstream.
Worked example

Assembly takes a 20-part container from the supermarket. What does the signal authorize?

A move kanban authorizes withdrawal or transport. A make kanban authorizes upstream production of one replacement container. The quantity is tied to what assembly used.

Process maps for different questions

Define the customer, trigger, and final output, then walk the real process. Map the work in sequence and look for decisions, handoffs, waiting, transportation, and repeat work. Choose the map based on what you need to learn.

SIPOC
Suppliers, inputs, process, outputs, and customers. Use it to agree on the scope and boundaries of a process.
Block diagram and flowchart
A block diagram shows the main components or stages. A flowchart traces activities and decision paths in order.
Swimlane diagram
A flowchart with a lane for each role, team, or system. An arrow crossing a lane marks a handoff to investigate.
Flow process chart
Records operations, inspections, transport, delays, and storage so that time and movement are visible alongside the work.

Value stream mapping and the ACME case

Choose one product family and trace its material and information flows from the customer upstream. On the current-state map, record observed cycle times, changeovers, uptime, batch sizes, and inventory, then compare elapsed lead time with processing time. On the future-state map, design to takt, connect steps in continuous flow where feasible, use controlled pull where flow breaks, and schedule the pacemaker. Use an implementation plan to close the gaps between the maps.

Pacemaker
The point that receives the production schedule and sets the pace for upstream replenishment.
Pitch
Takt time multiplied by pack quantity. It is a regular interval for releasing and picking up work at the pacemaker.
Worked example

ACME’s steering brackets take 23.6 days to move through the current stream, with 188 seconds of processing. What changes in the proposed design?

Combine welding and assembly into the pacemaker cell. Keep stamping in batches and replenish the cell through a supermarket. Shorter changeovers help the cell alternate product variants in 20-piece trays. At 60 seconds of takt, one tray is a 20-minute pitch.

Line balancing and precedence

Divide available time by required output to get the target cycle time. Round total work content divided by that target up to get the theoretical minimum number of stations. Draw the precedence diagram and assign tasks so that each predecessor is completed before its successor and each station stays within the target. Task sizes and precedence can make the actual station count higher.

Line efficiency
Total work content divided by the number of stations times the target cycle time, multiplied by 100.
Idle time and balance delay
Idle time per cycle is the number of stations times target cycle time minus total work content. Balance delay is 100% minus line efficiency.
Worked example

The spreader example has 244 seconds of work, a 60-second target, and a feasible five-station assignment. How efficient is the balance?

The lower bound is five stations after rounding 244 ÷ 60 up. With five stations, efficiency is 244 ÷ 300 = 81.33%, balance delay is 18.67%, and total idle time is 56 seconds across stations per cycle.

Time studies and allowance bases

Define the method and divide it into observable work elements. Time repeated cycles, document unusual events, and average the valid observations for each element. Multiply each average by its performance rating as a decimal and sum the results to get normal time. Add allowances for personal needs, fatigue, and unavoidable delays using the basis specified in the problem.

Allowance as a share of standard time
Standard time = normal time ÷ (1 − allowance). The allowance consumes that fraction of the final time.
Allowance as a share of normal time (CENEVAL convention)
Standard time = normal time × (1 + allowance). The allowance adds that fraction of normal time.
Worked example

Normal time is 15.36 minutes and the allowance is 15%. How does the choice of basis affect the result?

With the allowance as a share of standard time, 15.36 ÷ 0.85 is 18.07 minutes. With the allowance as a share of normal time, 15.36 × 1.15 is 17.66 minutes. The slide lists 17.64 for the second method. The values shown give 17.66.