Module 3 · Interactive practice
Production Line Lab
Change demand and cycle times to see which station limits output. The line has 60 production minutes per hour.
Line settings
60 units/h
45 s/unit
60 s/unit
50 s/unit
- Takt time
- 60 s/unit
- Line capacity
- 60 units/h
Cutting 45 s
Assembly 60 s
Inspection 50 s
Required takt time
Assembly is the bottleneck.
The line meets demand exactly.