Module 5

Lean Implementation

Start with customer value and a diagnosis of the current system. Use that evidence to choose a pilot, measure its effect, and decide how to sustain and extend the improvements.

Jump to practice

Transform the management system

Lean implementation is a strategic project that depends on leadership, a structure that supports work across functions, and employee participation. The course’s maturity path begins with preparation and diagnosis, moves to a focused pilot, then extends the approach across value streams. At maturity, employees and leaders use standard work, visual controls, and regular problem solving to improve how customer value flows through the organization.

Lean diagnosis
An assessment of current conditions in strategy, organizational structure, design, logistics, operations, and finance before choosing implementation priorities.
Pilot
A limited implementation where a team tests a change against a baseline and learns what it will take to extend it.

Business Model Canvas

The Business Model Canvas maps how an organization creates, delivers, and captures value. It has nine blocks. Customer segments, value propositions, channels, and customer relationships describe who receives value and how. Key activities, key resources, and key partners describe what makes the offer possible. Revenue streams and cost structure describe how the model earns income and what it costs to operate.

Worked example

An equipment maker offers monthly rental with maintenance to small clinics. Where does each part fit?

Small clinics are the customer segment. Access to reliable equipment with maintenance is the value proposition. Rental fees are a revenue stream, the machines are key resources, and servicing them is a key activity.

Deploy strategy with Hoshin Kanri and KPIs

Hoshin Kanri starts from mission, vision, and values. Set guidelines that name the priorities and objectives that define how much progress is needed from the baseline. Leaders and teams agree on strategies, assign projects and owners, and adjust the work through periodic reviews. Link each key performance indicator (KPI) to a decision. A line team may log stop minutes hourly, the value stream may review weekly on-time delivery, and leadership may review monthly strategic outcomes.

Level A · Value-added
Operating measures visible in the work area. The course shows hourly analysis in daily tables, such as target output, actual output, and minutes stopped.
Level B · Value flow
Value-stream measures linked to operations and strategy. Teams review them weekly in a business box score, which can combine operating, capacity, and financial measures.
Level C · Corporate
Strategic measures for the organization, typically reviewed monthly in a balanced scorecard.

Deliver in increments with Scrum

Scrum helps a cross-functional, self-managing team handle complex work as requirements change. The team plans a short, fixed-length Sprint using an ordered Product Backlog, checks progress daily, and produces a usable increment. At review, the team inspects the result with stakeholders and adapts future work. Transparency, inspection, and adaptation support decisions based on what the team learns.

Product Backlog
An ordered, evolving list of work needed to improve the product.
User story
A short description of a need from the user’s perspective, including who needs it, what they want, and why it matters.
Worked example

A team is building a production board. What might it deliver in its first Sprint?

Start with a usable board where operators can see planned and actual output. Review it with operators and use their feedback to decide how to prioritize downtime reasons or alerts in the backlog.

Make normal and abnormal conditions visible

5S establishes an orderly workplace and makes missing items or abnormalities easier to notice. Sort removes unnecessary items. Set in order gives needed items labeled locations. Shine combines cleaning and inspection. Standardize defines repeatable routines. Sustain makes those routines a habit through ownership, checks, and training. Andon uses simple signals to make operating status or an abnormal condition visible in real time.

5S
Seiri (sort), Seiton (set in order), Seiso (shine), Seiketsu (standardize), and Shitsuke (sustain).
Andon
A visual or audible cue, such as a light tower or message, that communicates a condition and prompts a defined response from the right person.
Worked example

A work cell frequently discovers that an essential gauge is missing just as production starts.

Give the gauge a marked point-of-use location and add a check to the startup routine. If the gauge is still missing, use an Andon signal with a named responder and a clear action.

Plan and follow up a Kaizen event

Kaizen is continuous improvement through repeated changes involving the people who do the work. A Kaizen event concentrates a team on a specific process and objective, typically for one to five days in the course’s general model. Before the event, define the scope, baseline, goal, sponsor, and team. Observe work at the gemba, record opportunities, test and implement changes, and report results and open actions. The course calls for four weeks of follow-up so process owners can stabilize and sustain the changes.

Opportunity card
A record of an observed issue and proposed improvement. The course groups cards into A (implement in 1–4 days), B (about 1–2 weeks), and C (more time or approval needed, up to two months).

Improve equipment effectiveness with TPM

Total Productive Maintenance (TPM) brings operators and maintenance specialists together to prevent losses. The six big equipment losses are breakdowns, changeover downtime, minor stops, reduced speed, process defects, and defects at startup or after changeovers. The six pillars in Module 5 are focused improvement, autonomous maintenance, planned maintenance, quality maintenance, training, and safety. Module 2’s eight-pillar graphic also includes early equipment management and office TPM, and labels safety as safety, health, and environment.

Availability × performance × quality
The three OEE factors are operating time ÷ planned production time, total units ÷ ideal output during operating time, and good units ÷ total units. Multiply them as decimals to get overall equipment effectiveness (OEE).
MTBF · Mean time between failures
Total operating time ÷ number of failures. It measures how long the equipment runs between failures on average.
MTTR · Mean time to repair
Total repair time ÷ number of failures. It measures how long it takes on average to restore operation.
Worked example

A 420-minute shift includes a 20-minute scheduled break, 16 minutes of changeovers, and two breakdowns totaling 24 repair minutes. The ideal rate is 60 units per hour. There are 320 total units and 300 good units. Find OEE, MTBF, and MTTR.

Use 400 planned minutes and 360 operating minutes. Availability is 360 ÷ 400 = 90%. Performance is 320 ÷ 360 ≈ 88.89%. Quality is 300 ÷ 320 = 93.75%. Using the unrounded factors gives 75% OEE. MTBF is 360 ÷ 2 = 180 operating minutes and MTTR is 24 ÷ 2 = 12 minutes.

Interactive practice

Classify the shift stops

A 480-minute shift includes a 30-minute scheduled meal break, 30 minutes of breakdowns, and 15 minutes of product changeovers. Classify the losses before using the OEE lab.

Which event is excluded from planned production time?

What time is available to actually run the equipment?

OEE lab

The scheduled 30-minute meal break leaves 450 minutes of planned production time. Set changeovers to 30 minutes, then set rejected units to 24. Which OEE components change at each step?

Move a slider or type an exact value.

Availability
90%
Starting 90%
Performance
88.9%
Starting 88.9%
Quality
96.7%
Starting 96.7%
OEE
77.3%
Starting 77.3%

OEE = availability × performance × quality. The sample uses an ideal cycle of 60 seconds per unit.

Improve delivery at a packaging cell

A packaging value stream has missed its delivery target for three weeks. The team has sponsorship for one small improvement event. Use the operating evidence to choose what to work on and how to follow up.

Evidence

Hoshin target

The annual priority is more reliable delivery. The value stream’s weekly on-time dispatch baseline is 84%, and the target is 96%.

Lost time

On the pilot cell, changeovers average 38 minutes and account for 14 of the 20 late dispatches. Breakdowns are infrequent and the first-pass yield is stable.

Gemba observation

Operators search for fixtures and instructions after the line has stopped. Both shifts say they could stage those items before changeover starts.

Team and pilot scope

The flow lead can sponsor a three-day event on this cell. Operators on both shifts, planning, and maintenance can take part. The proposed changeover target is 25 minutes.

Which action best supports the Hoshin priority?

Which measures should the team review after the event?

What should happen once the pilot meets its target?

Course references